Under the Briar Patch

Today we only had enough material for 3 batches of cement to spray up on the West retaining wall.  There will be more to do next week before the waterproofers come the following Monday.  They will be working from the ground up on the North side and will only go as high as they can reach.  We will need to bring in fill material and berm up to that level.  The contractor will then come back and continue up and over the shell.

But before we can start the berm, we need to extend the waterline that goes to the hose bibs on the East and South sides of the house.  Time for Dozy to do some digging.

Leave a Reply

Your email address will not be published.