North Meets South

The weekend started with a trip to Portland to pick up two sets of  3’ X 10’ X 6’ scaffolding (Craigslist find), that the shotcrete operator will need to reach the upper areas of the shell.  This also turned out to be really helpful for placing the foam forms on the inside of our shell.  The house is really starting to take shape now that we are putting the forms in.

 

pastedGraphic.pdf

 

pastedGraphic_1.pdf

 

pastedGraphic_2.pdf

 

It’s interesting how our house is starting to feel bigger now that it is getting closed in.

 

 

 

By the end of the of the weekend, we had managed to finish the East wing and the first row on the South side.  There is still a lot to do before we can spray the shell but the sense of progress is rewarding.

 

Leave a Reply

Your email address will not be published.